Mbira toll road
Based on mbira-toll-road-model.xlsm
A 25-year road concession with toll gates that open as each road section is finished, six vehicle classes, DSCR-based sizing with a year-by-year DSCR profile, and DSRA and MMRA reserves. Construction is modelled monthly on separate sheets and summed into a quarterly main timeline. Design example: written in the full v0.5 language. The compiler builds the working core today, so this one doesn't compile yet. Source: examples/design/toll/.
- Workbook
- 27 sheets: monthly construction sheets (ConTime, ConCost, ConFin), quarterly for the rest
- Timeline
- Rulers start Oct 2024, FC 31 Dec 2024, 36 months construction, 25-year concession
- Revenue
- 4 gates x 6 vehicle classes, 2018 AADT counts, class-specific traffic growth
- Capital
- Roadworks USD 141.0m, 70% gearing or DSCR sizing, 15-year sculpted term loan with 1-year grace
- Scenarios
- Base case 1 (4 gates), Base case 2 (2 gates, active), Base case 3 (3 gates)
- Rebuild shown
- 10 files, 187 lines, plus the shared concession package
Where each sheet goes
| Workbook sheets | Rufineer |
|---|---|
| Guide | style.rfn (colour key) and doc comments |
| InpC, InpS, InpS-m, InpS-a | inputs/*.rfn, with tables read from sheets of toll_inputs.xlsx |
| ConTime, Time | timeline with detail month |
| ConCost, ConFin | monthly modules cons_cost.rfn, cons_fin.rfn |
| Esc, Rev | rev.rfn |
| Ops, Acct, Tax, Equity | concession package (ops.rfn, tax.rfn, equity.rfn) |
| Debt, DSRA, MMRA | debt.rfn, reserves.rfn |
| Solve | generated from two solve lines |
| Metrics, S&U, FS Qtr, FS Ann, Output, Check | concession package (metrics.rfn, statements.rfn, checks.rfn) |
| Change, Tmp | not needed: version control replaces the change log |
Source 10 files shown, 187 lines
model "Mbira Toll Road" {
currency USD
data "toll_inputs.xlsx" // tolls, traffic counts, fees, curves
include "../concession" // shared with the Border Post model
}
timeline {
start 2024-10-01 // financial close 2024-12-31
fiscal_year ends Dec
step quarter
construction 36m detail month // monthly sheets for construction, like ConTime
operations until construction.start + inputs.concession
}
list vehicles = [light, minibus, bus, heavy, haulage, abnormal]
// the gates come from the rows of the Gates table/// Tables are sheets of toll_inputs.xlsx (named in model.rfn). Scalars stay here.
table toll: USD/vehicle sheet "Tolls" {
rows phase
columns light "Light motor vehicle", minibus, bus, heavy, haulage,
abnormal "Abnormal load"
}
/// 2018 classified AADT on the approach to each gate
table aadt: vehicle/day {
rows gate "Toll gate"
columns light "Light motor vehicle", minibus, bus, heavy, haulage,
abnormal "Abnormal load"
}
table growth: %/y { // low-growth case, feasibility report
rows vehicle "Vehicle class"
columns rate "Growth rate"
}
table gates {
rows gate "Toll gate"
columns opens: date "Opens",
through_share: % "Through traffic (heavy and haulage)"
}
inputs "Tolls and traffic" {
concession = 25y
active_gates = [chidza, nyuni] // Base case 2
cpi = 3.64 %/y @source "US 5-year average 2018-2022"
operations_cost = 13.5 % @note "12.5% per feasibility report plus 1% social"
}inputs "Construction" {
roadworks = 140_964_321 USD @note "includes 5% contingency"
plaza = 3_735_410 USD // two gates
toll_software = 1_000_000 USD
rams = 2_000_000 USD
idbz_review = 30_000 USD
maintenance = 69_725_700 USD // routine and periodic, whole concession
}
table construction_fees: % // Fee | Share of construction amount
table transaction_fees: % // Fee | Share of project costs
table spend_curve: % // Month ending | Spend
table maintenance_curve: % // Quarter ending | Spend
table forward_curve: %/y // Quarter ending | Rate
inputs "Financing" {
gearing = 70 %
swap_rate = 5.79 %/y @source "6m USD LIBOR swap, 17 Nov 2023"
margin = 6.00 %/y
hedged = 80 %
term = 15y
grace = 1y
sizing = option leverage | dscr // base: dscr
profile = option level_principal | sculpted | level_debt_service
dscr_profile = series by operations.year { 1..25: 1.10 } x
upfront_fee = 1.25 %
commitment_fee = 0.50 %/y
share_capital = 72_023_659 USD
shl_rate = 12 %/y
dsra_rule = option half_of_12m | next_6m | next_3m // base: next_3m
mmra_cover = 12m
cit_rate = 24.72 %
tax_depreciation = 1.14 %/q
discount_rate = 12 %/y
}module rev "Revenue" {
for g in inputs.gates {
period open[g] = inputs.gates[g].opens to operations.end
}
for v in vehicles {
traffic_index[v] = grow(inputs.growth[v], from: timeline.start) // one value column, so no .rate needed
fee[v]: USD/vehicle = (if construction then inputs.toll[construction, v]
else inputs.toll[operations, v])
| grow inputs.cpi yearly in Dec
}
for g in inputs.active_gates, v in vehicles {
through[g, v] = if v in [heavy, haulage] then inputs.gates[g].through_share else 0 %
count[g, v]: vehicle = inputs.aadt[g, v] * traffic_index[v] * period.days
* (1 - through[g, v]) | during open[g]
revenue[g, v]: USD = count[g, v] * fee[v]
}
total: USD = sum(revenue[*, *])
}/// Lives on the monthly construction ruler, like the ConCost sheet
module cons_cost "Construction costs" monthly {
base: USD = spread(inputs.roadworks + inputs.plaza + inputs.toll_software + inputs.rams,
over: construction, profile: inputs.spend_curve)
for f in inputs.construction_fees {
fee[f]: USD = base * inputs.construction_fees[f]
}
idbz: USD = inputs.idbz_review | at construction.first
project_costs: USD = base + sum(fee[*]) + idbz
for t in inputs.transaction_fees {
transaction[t]: USD = inputs.transaction_fees[t] * sum(project_costs)
| at construction.first
}
prefunding: USD = reserves.dsra.initial + reserves.mmra.initial + ops.wc.initial
| at construction.last
total: USD = project_costs + sum(transaction[*]) + prefunding
}module cons_fin "Construction funding" monthly {
/// "Project costs / funding requirement - paste" on the Solve sheet
solve requirement: USD = cons_cost.total + fees + idc
funding requirement {
first share_capital up to inputs.share_capital
then shareholder_loan up to equity.shl_commitment
then construction_debt rest
}
balance construction_debt: USD {
+ funding.construction_debt
- converted
}
converted: USD = construction_debt.opening + funding.construction_debt
| at construction.last // becomes the term loan
idc: USD = construction_debt.opening * (inputs.swap_rate + inputs.margin)
upfront: USD = inputs.upfront_fee * debt.size | at construction.first
commitment: USD = (debt.size - construction_debt.opening) * inputs.commitment_fee
fees: USD = upfront + commitment
}module debt "Senior debt" {
period repayment = (operations.start + inputs.grace) for inputs.term
all_in: %/y = inputs.hedged * inputs.swap_rate
+ (1 - inputs.hedged) * inputs.forward_curve
+ inputs.margin
/// "Cash flow available for senior debt - paste" on the Solve sheet
solve cfads: USD = cash.cfads
target_dscr: x = inputs.dscr_profile[operations.year]
capacity: USD = npv(cfads / target_dscr | during repayment, rate: all_in)
size: USD = match inputs.sizing {
leverage => inputs.gearing * sum(cons_fin.requirement)
dscr => capacity
}
// cons_fin.converted is monthly. Read here, it is summed into the quarter.
balance senior: USD {
+ cons_fin.converted
- principal
}
interest: USD = senior.opening * all_in
principal: USD = match inputs.profile {
level_principal => size / count(repayment)
sculpted => cfads / target_dscr - interest
level_debt_service => pmt(all_in, periods_left(repayment), senior.opening) - interest
} | during repayment
debt_service: USD = interest + principal
}module reserves "DSRA and MMRA" {
dsra_target: USD = match inputs.dsra_rule {
half_of_12m => 50 % * (debt.debt_service | next 12m)
next_6m => debt.debt_service | next 6m
next_3m => debt.debt_service | next 3m
}
dsra = reserve(target: dsra_target, initial: at construction.end)
mmra = reserve(target: ops.maintenance | next inputs.mmra_cover,
initial: at construction.end)
}scenario four_gates "Base case 1 (4 toll gates)" {
inputs.active_gates = [chidza, tonde, nyuni, pfuma]
inputs.plaza = 7_470_821 USD
inputs.toll_software = 2_000_000 USD
inputs.dscr_profile = series by operations.year { 1..8: 1.60, 9..11: 1.70, 12..: 1.60 } x
}
scenario base "Base case 2 (2 toll gates)" {}
scenario three_gates "Base case 3 (3 toll gates)" {
inputs.active_gates = [chidza, tonde, nyuni]
inputs.plaza = 5_603_116 USD
inputs.toll_software = 1_500_000 USD
inputs.dscr_profile = series by operations.year { 1..4: 1.40, 5..: 1.50 } x
}/// The Guide sheet's colour key, stated once
style {
font "Calibri"
inputs fill #FFFFCC
imports font #0000FF // from another sheet
exports font #FF0000 // used on another sheet
separators fill #DDEBF7
checks ok #C6EFCE error #FFC7CE alert #FFEB9C
tabs inputs #FFFFCC monthly #D9D9D9 outputs #DDEBF7 checks #CCFFFF
}What this model needed from the language
- A monthly construction ruler beside a quarterly main ruler. The workbook keeps ConTime, ConCost and ConFin monthly and sums them into quarters in Timeline aggregation blocks.
detail monthplusmonthlymodules generate the same layout, and the aggregation rows are written for you. - Two-dimensional tables and loops. AADT is gate by vehicle class, read from an Excel Table.
for g in inputs.active_gates, v in vehiclesproduces one row per pair, which matches the Rev sheet. - A period per gate. Each gate starts earning when its road section is finished.
period open[g]gives each gate its own flag. - Scenario-driven structure. The three base cases change which gates exist. The scenario sets
active_gates, and every loop that reads it changes shape.