Edge cases

The awkward parts of real models, one recipe each: the problem in plain words, the Rufineer that solves it, and the model where it came up. Written in the planned language: many recipes don't compile yet.

Time

COD in the middle of a period

Operations start on 15 May but the columns are quarterly, so the first quarter should only earn about half a quarter of revenue.

Rufineer
revenue: USD = energy * tariff * operations.share

operations.share is the fraction of the period's days inside the phase: 1 in full periods, about 0.52 in that first quarter, 0 outside. A plain | during operations treats the quarter as fully operating.

Monthly columns for the first operating year

Lenders want to see the ramp-up month by month, then quarterly for the rest of the loan.

Rufineer
timeline {
  start         2027-01-01
  construction  18m   step month
  operations    25y   step month for 12m, then quarter
}

The ruler changes width once. Every line converts its annual rates with the right year fraction in each column.

Monthly before COD, six-monthly afterSeen in Coral Bay, Oriole

The model runs monthly through development and construction and switches to half-years at commercial operation.

Rufineer
timeline {
  start         2018-01-01
  development   12m
  construction   3m
  operations    25y
  step          month until operations.start, then half
}

The switch point can be any date or phase start.

Phases with their own datesSeen in Oriole

Three solar phases reach financial close a year apart, each with its own construction period and 25-year life.

Rufineer
timeline {
  start  2019-01-01
  for s in stages {
    construction[s]  from inputs.stages[s].financial_close for inputs.stages[s].build
    operations[s]    25y
  }
}

module phase[s] "Phase {s}" for s in stages { … }

Each stage gets its own flags and counters, and each module declared for s in stages becomes one sheet per stage.

A payment on one date

A USD 250k licence fee falls due on 15 June 2031, inside a quarter.

Rufineer
licence_fee: USD = 250_000 USD | at 2031-06-15

The amount lands in the column that contains the date.

Escalation on an anniversary monthSeen in Oriole

The PPA tariff steps up every August from COD, not in January.

Rufineer
tariff: USD/MWh = inputs.tariff | grow inputs.escalation yearly in Aug from operations.start

yearly makes a step once a year; without it, the index grows every period.

Actuals for past periods

An operating model needs recorded revenue for the first two years and forecasts after that.

Rufineer
revenue: USD = energy * tariff | actuals "Revenue" until 2026-06-30

Past periods read the Actuals sheet of the data workbook by row label. The formula row is still there, so the switch-over is visible.

Monthly operations, six-monthly debt, yearly taxSeen in PPP road (Dakar)

Traffic is modelled monthly, debt is paid in May and November, and tax is yearly.

Rufineer
ruler monthly  month
ruler finance  half  ends May, Nov
ruler annual   year  ends Dec

module traffic "Traffic" on monthly { … }
module debt    "Debt"    on finance { … }

Revenue read by the debt module is summed into each half-year for you.

A daily loanSeen in Daily Bond

A development loan accrues interest daily with draws on specific dates.

Rufineer
ruler daily  day   from inputs.advance_date
module bridge "Bridge loan" on daily {
  balance loan: GBP { + draws  + capitalised  - redemption }
  interest: GBP = loan.opening * 12 %/y | day_count act/365
}

A rate that resets with a delaySeen in Aframax tanker

Charter rates follow the market with a three-month lag.

Rufineer
charter_rate: USD/d = inputs.market_rate | lag 3m

Days of an outage inside a monthSeen in Aframax tanker

A 25-day dry-dock starts on the 20th and runs into the next month.

Rufineer
period drydock[k] = inputs.drydocks[k].start for inputs.drydocks[k].days
off_hire: d = sum(overlap(drydock[*]))
charter_days: d = period.days - off_hire

Money

A debt currency chosen by a switchSeen in Coral Bay

The loan can be in pesos or dollars. Everything that touches it must follow the choice.

Rufineer
debt_currency = option MXN | USD

balance loan: inputs.debt_currency {
  + funding.debt in inputs.debt_currency
  - principal
}
debt_service_usd: USD = (interest + principal) in USD

A unit can be an option. Conversions follow the switch through the fx row.

FX forecast from inflationSeen in Coral Bay

The peso is forecast from purchasing-power parity, with a separate real change on top.

Rufineer
fx MXN/USD = ppp(17.53, local: inputs.macro.mx_cpi, foreign: inputs.macro.us_cpi)
           * grow(inputs.macro.real_fx_change)

Returns in three termsSeen in Coral Bay

The summary shows project IRR in dollars, in pesos and in real dollars.

Rufineer
irr_usd  = xirr(project_cash)
irr_mxn  = xirr(project_cash in MXN)
irr_real = xirr(real(project_cash, by: inputs.macro.us_cpi, base: timeline.start))

P90 and P99 from a standard deviationSeen in Coral Bay

The yield report gives a P50 and an uncertainty of 6%. The model needs P90 and P99.

Rufineer
p90: kWh/kWp/y = pvalue(inputs.p50, sd: 6 %, level: 90)     // 1,985.5 → 1,832.8
p99: kWh/kWp/y = pvalue(inputs.p50, sd: 6 %, level: 99)     // 1,985.5 → 1,708.4

Written as p50 × (1 − NORM.S.INV(level) × sd) in the workbook.

A levelised provisionSeen in Coral Bay

Inverters are replaced every 10 years. The model books a flat yearly provision with the same present value.

Rufineer
replacements: USD/kW = inputs.inverter_cost | grow 1.5 %/y | every 10y from operations.start
provision:    USD/kW/y = level(replacements, rate: 10 %/y)     // 4.17 USD/kW/y

level also adds a check that the two NPVs match, like the workbook's Proof rows.

Capture price from hourly dataSeen in Big Model with Battery

Prices and solar output come as 8,760-hour profiles; the model needs a yearly price.

Rufineer
capture_price: USD/MWh = weighted_avg(inputs.prices_8760[year], by: inputs.solar_8760)

Hour-of-year tables are reduced to yearly factors; the timeline stays monthly or longer.

Profit oil on an R-factorSeen in Oil PSC

The contractor's share of profit oil falls as cumulative revenue grows relative to cumulative cost.

Rufineer
r_factor = cumulative(contractor.revenue) / cumulative(contractor.cost)
profit_share = bands(prev(r_factor), { ..1.0: 50, 1.0..1.5: 45, 1.5..2.0: 40, 2.0..: 30 } %)

prev uses last period's R-factor, as most contracts do, which also avoids a loop.

Debt

Size on two cases at onceSeen in Coral Bay

Debt is the lowest of 80% of cost, P50 CFADS at 1.35x and P99 CFADS at 1.00x.

Rufineer
by_p50: USD = npv(cash.cfads / 1.35 x | during tenor, rate: all_in)
by_p99: USD = npv((cash.cfads under p99) / 1.00 x | during tenor, rate: all_in)
solve size: USD = min(0.8 * capex.total, by_p50, by_p99)

under p99 builds the P99 cash flows on a parallel sheet. No second copy of the model to keep in step.

Several tranches with their own termsSeen in Oriole

Senior 1, 2 and 3 and a mezzanine loan each have their own share, tenor, rate, fees and repayment profile.

Rufineer
for t in inputs.tranches {
  loan[t] = term_loan(
    amount:  inputs.tranches[t].share * senior_size,
    rate:    inputs.tranches[t].rate,
    window:  operations.start + inputs.tranches[t].grace for inputs.tranches[t].maturity,
    profile: inputs.tranches[t].repayment
  )
}
debt_service: USD = sum(loan[*].debt_service)

The terms come from a sheet of the data workbook. Adding a tranche is adding a row.

One facility on a different day countSeen in Oriole

The model is Actual/365, but one loan accrues on 360 days.

Rufineer
interest: USD = loan.opening * rate | day_count act/360

A fee that includes itselfSeen in Coral Bay

The development fee is 5% of total cost, and total cost includes the fee.

Rufineer
function gross_up(base, rate) = base * rate / (1 - rate)
development: USD = gross_up(epc.total, 5 %)       // 708.58 → 37.29 USD/kW

Solve it with algebra, not a loop.

DSRA funded in cash or by a letter of creditSeen in Oriole

A switch decides whether the reserve is cash on the balance sheet or an LC with a fee.

Rufineer
when inputs.dsra_mode == funded {
  dsra = reserve(target: debt_service | next 6m)
}
when inputs.dsra_mode == letter_of_credit {
  lc_fee: USD = (debt_service | next 6m) * inputs.lc_fee_rate
}

A borrowing base redetermined twice a yearSeen in Oil RBL

The reserve-based loan may not exceed 45% of the present value of remaining reserves.

Rufineer
borrowing_base: USD = 45 % * pv_ahead(net_revenue, rate: 8 %/y) | sampled every 6m
mandatory: USD = max(0, rbl.opening - borrowing_base)

A bid tariff at a target returnSeen in PPP road (Dakar)

The concession is bid at the toll that gives equity 15%.

Rufineer
seek inputs.toll so that returns.equity_irr = 15 %

A Seek macro with a check, or algebra when the return is linear in the toll.

Refinancing a mini-perm

A seven-year mini-perm with a 60% balloon is refinanced by a sculpted term loan.

Rufineer
mini = term_loan(amount: debt.size, rate: 6 %/y, window: 7y, profile: balloon(60 %))
refi = refinance(mini, at: mini.window.end,
                 with: sculpted_loan(rate: 6.5 %/y, window: 15y, cfads: cash.cfads, dscr: 1.30 x))

Equity

Up-front equity, then pro rataSeen in Oriole

Sponsors put in 40% of their equity before any debt is drawn, then fund pro rata with the lenders.

Rufineer
funding uses {
  first  equity  up to 40 % * equity.commitment
  then   pro_rata {
    senior  share 75 %
    equity  rest
  }
}

Planned as a drawdown order (equity_first 40 % of equity, then pro_rata); written by hand for now.

A partner with a carried interestSeen in Oriole

The state utility holds 5% of the project without putting in capital.

Rufineer
split to_equity {
  main_investor  95 %
  edm             5 %   carried
  funded by      equity_draws
}
main_irr = xirr(to_equity.main_investor)

The main investor funds all draws and receives 95% of distributions, which is why its IRR sits below the project's equity IRR.

A promote above a hurdle

Investors take everything until they earn 12%, then the developer gets 20%.

Rufineer
split to_equity {
  first  investors 100 %              until investors earn 12 %/y
  then   investors 80 %, developer 20 %
}

A tax equity yield flipSeen in Tax equity course model

The investor takes 95% of cash and income until it earns its target yield, then 15%.

Rufineer
split partnership among tax_investor, sponsor {
  cash   = cash.distributable   tax_investor 95 % until flip, then 15 %
  income = tax.taxable_income   tax_investor 95 % until flip, then 15 %
}
event flip = first(earned(partnership.tax_investor.after_tax, 5 %/y))

Structure

Features on a switchSeen in Coral Bay

Inverter replacement is modelled but switched off in the base case.

Rufineer
when inputs.include_inverters {
  inverter_provision: USD = capacity * provision
}

Rows stay in place when the switch changes; switched-off lines read as zero.

A construction S-curve from a distributionSeen in Oriole

Spend follows a beta curve with alpha 9 and beta 2 rather than a typed table.

Rufineer
spend: USD = spread(epc.total, over: construction, profile: beta(9, 2))

Also even, normal(mid, sd) or a table from the data workbook.

The whole model on one sheetSeen in Coral Bay

A small model is easier to read on a single sheet, like Coral Bay's Financial Model.

Rufineer
model "Coral Bay Solar" {
  sheets  one
}

Modules become titled sections of one sheet, and the Imports blocks disappear because nothing crosses a sheet.

A formula Rufineer cannot express

A lender insists on a specific Excel construct.

Rufineer
special: USD = excel "=MAX(0,{rev}-{cost})*{flag}"
               with rev: ops.revenue, cost: ops.opex, flag: operations

References still go through the sheet's Imports block. rfn check lists every excel line.

Maths you repeat

Several costs are quoted per kW and converted the same way.

Rufineer
function per_kw(amount, capacity) = amount / capacity
om: USD = per_kw(inputs.om_budget, 1 kW) * plant.capacity

Functions are written out in full where they are used, so there is nothing hidden in VBA.

One template sheet per assetSeen in Telecom Portfolio

Sixteen cell towers share one template; some are excluded from the consolidation.

Rufineer
module tower[t] "Tower {t}" for t in inputs.towers where inputs.towers[t].include == yes { … }
ebitda: USD = sum(tower[*].ebitda)

Overhaul by running hoursSeen in Merchant Plant Model

A gas turbine is overhauled every 25,000 operating hours, and output falls during the outage.

Rufineer
running_hours: h = period.days * 24 h/d * capacity_factor
overhaul: USD = inputs.overhaul_cost | every 25_000 h of running_hours

Funding

Debt pro rata with the equity, shareholders in orderSeen in Tutorial 2 (Mopane)

The senior loan pays its share of every quarter's uses from financial close and is fully drawn at COD; preference shares, a shareholder loan and the ordinary shares pay the rest in order of seniority, each up to its commitment.

Rufineer
drawdown {
  before financial_close: ordinary
  from financial_close: pro_rata on uses
  equity in_order [pref_a, shl, ordinary]
}

senior = loan(size: 70 % of costs, interest_during_construction: paid, …)
shl    = loan(by: shareholders, size: inputs.shl_size, …)
shares pref_a   up to inputs.pref_a
shares ordinary = rest

In the model block. The loan's share is its size over the uses from financial close, solved when the uses include interest and fees on what it draws.

Equity first, then the loanSeen in Tutorial 3 (Msasa)

The partners pay their 40% before the bank lends anything, so the bank's money goes in last.

Rufineer
drawdown equity_first

loan = loan(size: 60 % of uses, signed: base_case, upfront_fee: 1.25 %, …)
shares partners = rest

The rest's amount is the uses less every other source; it pays that first, then the loans side by side, then anything still left. in_order [partners, loan, overrun] puts a capped class first and an overrun last.

Back-ended equity

The lenders fund construction to their commitment first; the sponsors' equity comes in at the end.

Rufineer
drawdown debt_first

back_ended says the same. The loans draw side by side, by their sizes, then the equity in order.

Two lenders side by side, a mezzanine first

The mezzanine funds first; the commercial bank and the DFI then lend pari passu; the sponsors pay the rest.

Rufineer
drawdown {
  from financial_close: in_order [mezz, [senior, dfi]]
}

Sources in [ ] share what is left by their sizes. The rest comes last, named or not. Drawing order is separate from repayment rank (rank:).

A loan sized on every use, fees and IDC includedSeen in By hand (Highveld)

The lenders size the loan at 75% of total project cost, which includes the loan's own arrangement fee and interest during construction.

Rufineer
senior = loan(size: 75 % of uses, upfront_fee: 2 %, commitment_fee: 0.5 %/y,
              interest_during_construction: paid, …)

of costs is the capex before financing costs, with no loop. of uses is circular, and Rufineer writes the total as a solve line.